Every two weeks, meetings are held with the contractors and subcontractors.
As of today August 21st 2019,
- Wired fencing around the property is done.
- Encroachment issue with the neighbor has been resolved.
- Electric poles and wires that were passing through the masjid property have been re-routed by “OnCore”.
Approximately 60 trucks of soil / dirt that has been brought to the Masjid site. A majority of the excavation has been done. In the upcoming week, excavation of the remaining land is scheduled to take place.