Masjid Exterior Remediation work has begun and is on schedule:
- contractor is in the process of completing the pre-construction submittals.
- The balcony work is complete except for minor adjustments to the installed door. Contractor to make the adjustments.
- Contractor warranty has been received. manufacturer warranty has been requested. The warranties will be included in the warranty manual for the exterior wall project.
- Contractor observed the railing around the a/c on the roof is leaking. It was asked if contractor could remove the railing and seal the holes in the roof that will be exposed when removed.
- Contractor will review the railing and respond on whether there will be a cost associated with the removal and sealing. Contractor was asked to dispose of the railing after removal.
- In commemoration of World Food Day -Plano Jamaat celebrated the partnership by McKinney Little Free Pantry by donating essential food items. A Representative from the Pantry visited the Masjid to give an overview into the NGO. A speaker from Umoor FMB also spoke to farzando about the nemat of Aqa Moula (tus) nu Jaman, khidmat, and logistics.