On Saturday, August 28, 2021 – a progress meeting was held at the Masjid Site.
Meeting Details:
- Discussion focused on completion of tile work and modifications of areas where tiles need to be relaid.
- Temporary interior railings have been completed as the Mahogany Railings are under fabrication and will take another 45 days.
- Exterior railings were completed today.
- Kitchen equipment is scheduled to be delivered on Thursday.
- Schedule for carpet laying was discussed. It was decided that in order to preserve the carpet, the carpet would be laid after all masonary work for Qibla and other polish work is completed.
- Electrical final inspections will be called in on Wednesday.
- Painting work is in progress – 2nd floor ceiling is done. Wall painting will be starting from Wednesday.