The Dawoodi Bohra Community of Collin County, TX

Plano Masjid Progress Update – Friday, April 22, 2022

On Wednesday , April 20, 2022 – a mediation meeting was held at the Masjid Site with the Architect / Project Manager and Contractor.

Meeting Details:

  • A 3rd Party contractor has been brought on to do a walk through of the Masjid Site.
  • Via a mediated meeting concerning pay apps, work pending and retainage, we were able to amicably agree to move forward.
  • An issue came forward concerning lien from contractors. According to the City -The unconditional lien releases come from the paving and utility contractors listed on the Affidavit of Value who completed the public improvements (any construction, reconstruction, or upgrading of a water, sanitary sewer, or storm sewer line, public street including bicycle lanesor sidewalk or undergrounding of public utilities) on the project confirming that they have been paid.
  • The All Bills Paid Affidavit comes from the owner confirming that the GC has been paid. This pertains only to the public improvements of the project, and not the entire project.

    *These technicalities and clarifications are vital as we approach CO. *

    This morning we had an opportunity to do Live Deedar of Aqa Moula (tus).

    Moula (tus) heard our Araz ke “Moula Masjid Tayar Che, Moula Jaldi Plano Padhaaro”, ghana khush thaya, did nazar on us for an extended amount of time and “Inshallah” farmayu. It was a moment to remember.

    May we soon see the day when Moula (tus) Plano padhaare for the Iftetah of our Masjid. Ameen