On Saturday, May 8, 2021 – a progress meeting was held at the Masjid Site with the Architect and Contractor.
Meeting Details:
- Tiling work on the patio will start from Monday. Remaining tiling will begin from first week of June.
- Indian toilet has been ordered.
- The AV people will be at the site on Monday morning for the final review with the electrician.
- The framer will start his work starting Monday morning. He will finish the walls in two weeks and then start the ceiling work. The ceiling will be closed once the light fixtures are installed and inspection completed.
- Electrical inspection is slated to be done by May 17, 2021.
- Bathroom fixtures and faucets are being finalized.
- Elevator will be delivered by Mid June.
- The wooded door panels have been delivered to the site.
- The cast stone work has started – at the front entrance.
- Doors and window glass are under production.