Plano Masjid Progress Update – September 14th & 17th, 2020

On Monday, September 14, 2020 – a progress meeting was held at the Masjid Site with the Architect and Contractor.

Meeting Details:

  • Repair work for Stud is complete.
  • RTU screen design had to be modified due to layout of joists and size of RTU. Material to be on site on 9/16, anticipated completion 9/21.
  • Water Fountain bid to be submitted by GC on 9/18.
  • GC+ Arch + Owner will visit brick showroom before 9/18 to identify brick and stone color. Based on that selection GC will install 2 full size mockups with stucco color.
  • Architect – Mr. Fahim Khan to modify the chandelier locations in men’s and women’s grand hall.
  • GC will provide extra joist in Atrium for center chandelier.
  • Fence design samples were reviewed and an ornamental design was selected, design for fence to be discussed further.
  • Contractor to quote masonary + swing gates at 2 entrance and Picket fence around perimeter.

  • Chandelier Designs for Main Masjid Center, Bairao Masjid, Sahen and Fouyer were explored and design awaiting approval.

Thursday, September 17, 2020

The Masjid Committee visited the Stone and Brick manufacturer’s plant to finalize the Stone and Brick for the entire Masjid.

  • The Tone ane Color of the Stone was finalized, along with the Brick. The lead time is almost 45- 60 days.