Plano Masjid Progress Update – September 24th, 2020

On Saturday, September 27, 2020 – a progress meeting was held at the Masjid Site with the Architect and Contractor.

Meeting Details:

  • The steel columns, beams, joists are erected.
  • The second floor (Muminaat section) metal deck is installed and getting ready for the concrete pouring by next week.
  • Sidewalk along Tennessee street is done. The approaches to that sidewalk to be done by early next week.
  • The elevator order is placed and the pit is getting ready for swamp pump and oil separator.
  • The exterior metal framings for the walls are done.
  • The exterior sheathings on the metal frames are in progress.
  • The HVAC work is in progress.