Plano Masjid Progress Update – September 5th, 2020

Masjid Construction Progress meeting was held at the Masjid Site with the Architect and Contractor.

  • Extra material for Stud Framing is on site as of 9/5/20. Installation will start on 9/8, completion on 9/11/20.
  • Work on manhole will begin week of 9/7/20- subject to weather conditions.
  • Qibla framing on schedule for completion on 9/18/20.
  • Pavement and Flum Concrete – is planned to be poured on 9/8/20 – weather permitting.
  • RTU (Roof Top Unit – related to AC System) screen design submitted by Architect Fahim Khan. Material for the same to be on site by 9/11/20.
  • Angle enforcement for railing was reviewed. Drawings to be modified by Murtuza Bhai Tinwala and submitted to Structural Engineer – Mr.Kabir.
  • Fountain was discussed and GC will provide quote for a complete Fountain System.
  • The stone, brick and stucco color will be re-sampled and mock up put on sight, colors to match as per rendering presented.