Plano Masjid Progress Update – Sunday , October 31st, 2021

Masjid Related and Updates:

  • Atmos (Gas Company) has confirmed that the underground, riser, and meter will be installed at the end of this week / next week.
  • The final inspections for Gas and Health will happen after gas meter installation.
  • The final inspections for HVAC is done – passed.
  • Elevator is done. Pending now is the phone line.
  • Mumineen continue to visit the Masjid Site for many purposes – for discussions / meetings as well as more recently – to walk as part of “Miles for Moula (tus)”.